010-59602451
10 2021-05

DPDC 33kV Underground Cable Line Energized Successfully

On 9th may 2021 with Present of DPDC High officials along with CCC engineering Ltd. At GMT 2.11 Pm Motijheel 132/33kV GIS S/S to Kamlapur 33/11 kV S/S double circuit 33kV underground cable line energized successfully. CCCE & ETERN JV is the EPC contractor of this 33kV underground cable line Project. Where this 33kV underground cable project financed by Asian Development Bank (ADB).
07 2021-05

Site Monthly Inspection by High Officers from REG & EDCL

In the Mid of April, His Excellency the CEO of Rwanda Energy Group Ltd (REG) and Managing Director of Energy Development Corporation Limited (EDCL) paid a monthly visit to 110/30kV NYABIHU substation in Rwanda which was under construction by CCC ENGINEERING LTD. The Project Manager Mr. Cao Shoufeng of CCCE accompanied with high officers and gave detailed introduction for this project, as the Employer of this Project, all the representatives from EDCL applauded our performance and fast delivery o
10 2021-03

Energizing Successfully on Bangladesh Kazla Substation

The 132/33kV kazla GIS substation under Bangladesh DPDC Lot-1 project(7 NOS. 132/33KV GIS) )has been energized successfully on 9/3/2021. Director Engineering, Chief Engineer Development, Chief Engineer Grid, Superintendent Engineer Grid, Superintendent Engineer Protection were present.
05 2021-02

Notification of Award for Rwanda 220kV Bugesera Substation Project

The notification of contract award for DESIGN, SUPPLY AND INSTALLATION OF 220/110/30KV AUTOTRANSFORMER, CONTROL AND PROTECTION EQUIPMENT FOR BUGESERA SUBSTATION was issued by ENERGY DEVELOPMENT CORPORA…
02 2021-02

Bangladesh Shahjibazar 100MW Gas Turbine Power Plant Successfully Completed 168-Hour Reliability Te

The Shahjibazar 100MW Gas Turbine Power Plant Project contracted by our company successfully completed 168-hour Reliability Test Run and put into commercial operation at 09:00 a.m. on February 1th, 2021 local time in Bangladesh.This is the first LMS100 aircraft modified unit in Bangladesh and even in Asia. The owner of the project is Bangladesh Power Development Board (BPDB), and the GT model is GE LMS100.It has the advantages of fast start up and highly automated control, which can well meet th
29 2020-12

Advance Payment reveived for Power Grid Network Strengthen Project under PGCB

CCCE and its consortium members has fully received the downpayment for the subject mentioned project,which means financing closure for this project has been completed and the project is ready to be st…
09 2020-11

Signing Ceremony for Strategic Agreement between Siemens and CCCE

On the occasion of the third China International Import Expo, Siemens held a strategic agreement signing ceremony with us on 6th Nov for the project of Power Grid Network Strengthening Project under Power Grid Company of Bangladesh Limited. As a member of the consortium of the project, CCC Engineering Ltd. signed the strategic agreement with Siemens on behalf of Jiangsu ETERN Company Limited (the leader partner of the Consortium). The project is financed by the Export-Import Bank of China. Sieme
06 2020-11

Achieving Synchronization for Shahjibazar 100MW Gas Turbine Power Plant

At 14:08 local time on November 5th, 2020 in Bangladesh, Shahjibazar 100MW Gas Turbine Power Plant contracted by CCCE was successfully synchronized and connected to the grid.The Owner of the Plant is Bangladesh Power Development Board (BPDB). The Gas Turbine is GE LMS100, which is the largest aero-type GT in the world and has the advantages of fast start-up and high degree of automation, also can well meet the peak load operation. This LMS100 Aero Turbine is the first unit achieving synchronizat