Inauguration Ceremony of Samundratar Substation and Transmission Line in Nepal
The Samundratar – Trishuli 3B Hub 132kV Transmission Line Project,which was constructed by CCC Engineering Ltd, has been energized successfully on June-24,2021. The completed work includes New 132/33/11kV Samundratar Substation, Renovation of 33/11kV Chaughada Substation, Samundratar-Trishuli 132kV Overhead Transmission Line.
And a grand inauguration ceremony is hold on July-3,2021 at Samuntratar Substation. The Deputy Managing Director of Nepal Electricity Authority and Chief of Local Government are present.
Mr. K.P.Sharma Oli (Rt. Hon. Prime Minster of Nepal) joins the inauguration via virtual meeting, and then makes remote operation and delivers a congratulating speech, which is live cast through Nepal National TV channel.
Even impacted during the hard period of Covid-19 Pandemics, we have been keeping stable continuous project progress and maintaining the health plan and achieves the fruitful zero infection target in our project.
In recognition of our outstanding contribution to the power construction in Nepal, an appreciation certificate is issued to us, jointly by Managing director of NEA, Honorable Minister of Water Resource and Energy, and Prime Minister.